-A central station of total capacity 600 RT to supply the administration building and two social clubs with chilled / hot water for air conditioning system, by a district cooling / heating system.
- The heating system for the swimming pools, also includes Ebara direct fired absorption chillers.
- The HVAC cost
5.5 million Egyption pounds.
- GasCool scope of work:
Design, detailed engineering, procurement services, construction supervision and start up for District Cooling / Heating system, as well as supply of EBARA Absorption Chillers.
- The contract was signed on the 1st of February 2006.